Construction Updates

The following projects will provide a variety of construction improvements.
Please refer to the links below for your specific project. 

2021 Cambridge Project
Work Update: Installation of the new sanitary sewer along the west parkway of Cambridge Drive has been completed, and the new mainline water main throughout the project limits has been substantially completed. Please be advised that the Contractor will be working at the intersection of Cambridge Drive and University Drive this Saturday, September 18. Per the Village ordinance, the working hours are from 8 a.m. to 6 p.m. 

Monday, September 20 - Pending satisfactory testing results, the Contractor will start the installation of new water services on Cambridge Drive from Anthony Road to Middlesex Court, and on Anthony Road from Cambridge Drive to the east. Please see below for additional information. 
Tuesday, September 21 - Crews will continue installing new water services on Cambridge Drive from Anthony Road to Middlesex Court, and on Anthony Road from Cambridge Drive to the west. Please see below for additional information. 
Wednesday, September 22 - Crews will continue installing new water services on Anthony Road from Cambridge Drive to the west. Please see below for additional information. 
Thursday, September 23 - Crews will continue installing new water services on Anthony Road from Cambridge Drive to the west. Please see below for additional information. The Contractor will also be installing a new storm sewer at the intersection of Anthony Road and Cambridge Drive. A third crew will be connecting the new water main to the existing water main on Cambridge Drive, south of Middlesex Court. This work will require a water service interruption to several homes on Cambridge Drive, south of Middlesex Court. Please look for an additional notification letter on your front door prior to this date if it will directly affect your residence. 
Friday, September 24 - Crews will continue and finish installing new water services on Anthony Road, west of Cambridge Drive. Please see below for additional information. The Contractor will continue installing a new storm sewer at the intersection of Anthony Road and Cambridge Drive. A third crew will be installing new underdrains just south of Dundee Road on Cambridge Drive. 
Saturday, September 25 - The Contractor will finish the installation of the new storm sewer at the intersection of Anthony Road and Cambridge Drive. 

Upcoming Work: The Contractor will be finishing all underground improvements throughout the project limits north of Charles Court and restoration efforts will commence thereafter. Crews will continue with underground improvements south of Charles Court. 

Resident Impacts: 

•    Access to all homes will be maintained, except when work is being performed directly in front of your residence. This disturbance will only be temporary and full access will be restored with gravel for safe ingress and egress at the end of the working day.
•    Most of the work this week will occur on Cambridge Drive from Charles Court to Middlesex Court, and along Anthony Road. We encourage residents to find alternate routes and avoid this area.
•    If you wish to park off the project limits during the day or overnight, the Police Department has been notified that overnight street parking will occur; please park legally regarding all other laws and ordinances.

Additional Information:
The Contractor will attempt to complete as many water service installations as possible each day, therefore, the schedule above is an estimate based on planned production and a favorable weather forecast. The exact date of each water service disruption will be known through written notice to each residence's door the day prior to work is scheduled.

Keep in Mind: Due to material shortages, temporary stone will be placed where the existing sidewalk has been removed on Dundee Road. It is anticipated that the new sidewalk will be placed by the end of September. 

Planned work is subject to change based on several factors including the weather, Contractor availability and unforeseen circumstances. Motorists are urged to pay close attention to orange signs and flaggers in work zones, obey posted speed limits, avoid cell phone use, and be alert for construction workers and equipment. 

Thompson & Brandywyn Contract 2 Project
Thompson Boulevard:
Monday, September 20 - Tuesday, September 21 - The Contractor will be performing pavement patches at various locations from Buffalo Grove Road to Weiland Road. The roadway will be reduced to one lane during working hours so please pay attention to flaggers and expect delays. Crews will also be saw cutting and sealing joints in the new concrete curb. 
Wednesday, September 21 - Crews will be placing topsoil, seed, fertilizer and straw mulch within the disturbed parkways at any remaining locations. Please keep off the newly placed seed and refrain from mowing to promote a live, healthy turf area.  

Brandywyn Lane:
Wednesday, September 22 - Friday, September 24 - Crews will be performing punch list work at various locations throughout Brandywyn Lane and performing general site cleanup. 
Thursday, September 23 - Friday, September 24 - Crews will be placing topsoil, seed, fertilizer and straw mulch within the disturbed parkways along Brandywyn Lane from Aptakisic Road to Buffalo Grove Road. Please keep off the newly placed seed and refrain from mowing to promote a live, healthy turf area.  

Upcoming Work:
Parkway restoration will continue at various locations throughout the project limits and the final asphalt layer will be placed.

Resident Impacts:

Please continue to use caution while traveling through the work zone and pay attention for flaggers and staging areas. 

Planned work is subject to change based on many factors, including the weather, Contractor availability and unforeseen circumstances. Motorists are urged to pay close attention to orange signs and flaggers in work zones, obey posted speed limits, avoid cell phone use and be alert for construction workers and equipment.

2021 Melinda & Hiawatha Project
2021 Vintage Project 

Street Patching Project

Did you know that some roads in Buffalo Grove are owned and maintained by Cook County (CCDTH), Lake County (LCDOT), or the State of Illinois (IDOT)?
Click here for more information. 

Interested in learning about current projects being done by external organizations?

Lake Cook Road

Mainline paving operations on Lake Cook Road are ongoing as is bridge construction at the Lake Cook Road and Buffalo Grove Road intersection. Noise wall work is expected along the south side of Lake Cook Road east of Walmart.

Please click here for project updates and to sign up for Cook County's E-newsletter.  

Please click here for a project overview and timeline. 

Please note: This project is not confined to Lake Cook Road; construction (and lane closures) will occur on proximal areas of Buffalo Grove Road, Weiland Road and Route 83. Please click here for project updates and to sign up for Cook County's E-newsletter.

Weiland Road
Landscaping and restoration activities continue this week. Tree installation is expected to start soon pending appropriate planting weather and tree availability. 
  
Construction south of Deerfield to Armstrong Drive is complete. Construction traffic patterns remain in place approaching Lake Cook Road as construction to the south continues.

For the latest updates, time-lapse progress photos and drone footage, see Lake County’s project page here.

Buffalo Grove Road

9/10/2021 - Concrete curb and gutter installation is in progress on the west side of Buffalo Grove Rd from Aptakisic Rd to Deerfield Parkway. Also, crews are working on subgrade excavation for the new road base and storm sewer installation on Aptakisic Rd.

For week of 9/13, crews will work on curb/gutter installation, storm sewer and construct the new road base on Aptakisic Rd.

Traffic Impacts: Watch for workers and flaggers. Please be cautious of trucks coming in and out of the jobsite.

For the latest updates please visit the Lake County Buffalo Grove Road Construction Page to remain informed. Visit that page by clicking here where you can view the schedule and signup for updates from Lake County.

Pavement Patching Rt.83 (from US 45 to Buffalo Grove Rd.)